Communicating by radio

Contractors beware – pay attention to any directions that you may issue to subcontractors!

Ben Johnson ||

A recent Supreme Court decision has highlighted the importance of ensuring clarity in any notices or directions that head contractors or principals provide to subcontractors. If you have any role within a construction contract, it is important that you understand your rights and obligations.

Facts

The decision  of CPB Contractors Pty limited v Heyday5 Pty Limited [2020] NSWSC 1625 involved a dispute in relation to the construction of the new WestConnex M5 project in Sydney. Heyday5 Pty Ltd (Heyday), was engaged by a joint venture between CPB Contractors Pty Ltd, Dragados Australia Pty Ltd and Samsung C & T Corporation (CPB) to undertake electrical works related to the tunnel (Contract).  The Contract was dated 9 July 2018.

As with many standard contracts, the Contract gave CPB the right to direct Heyday to increase, decrease or omit any part of the work under the Contract. The Contract also required Heyday to maintain safe work method statements (SWMS), and provide copies of the relevant SWMS to CPB before the commencement of works under the Contract, or periodically throughout the progression of the works to be performed by Heyday.

To complete the work that was the subject of the Contract, Heyday was required to use mobile elevated work platforms. As part of the operation of the platforms, a driver was required, as was a spotter on the ground to alert the driver of any dangers.

Accordingly, Heyday then provided a number of SWMS to CPB in accordance with the Contract for the use of these platform. As part of the first SWMS provided to CPB on 2 July 2018, it was an express term that the driver of the platform must maintain visual contact with the spotter. A further SWMS was provided to CPB on 12 December 2018, which was drafted differently to that of the first SWMS.

Following the publication of a work and safety report in South Australia in early 2019, CPB issued a direction to all subcontractors engaged in the construction of the M5 WestConnex (including Heyday) that stated that at all times when the platforms were being used, all spotters were required to be within the sight of the driver, and within a short enough distance to allow verbal communication between the driver and the spotter.

Heyday then claimed that this direction was in fact a variation under the Contract. CPB contended that this direction was not a variation as Heyday (and all subcontractors) were required, under both the Contract and the work health and safety legislation, to provide spotters to eliminate any risks that may arise from using these platforms. It would follow, under the position taken by CPB that any direction with the effect of confirming the obligations of subcontractors in terms of both the Contract and relevant legislation is not a variation to the contract.

Court Proceedings

The matter became the subject of an adjudication application by Heyday, in which the adjudicator determined that the direction resulted in a variation under the Contract. The variation, as the adjudicator determined, caused additional costs for Heyday, and as such they were entitled to the recovery of those costs.

CPB sought to set aside the adjudicator’s determination on two grounds, being that the determination of the claim for spotters by Heyday was unintelligible, and that Heyday’s claim for a spotters fee was determined on a basis on which neither party made submission in either of the adjudication applications.

The Court acknowledged that components of the adjudicator’s determination could have been expressed differently, but that it is not otherwise unintelligible as submitted by CPB.  CPB failed on the first ground.

In respect of the second ground of appeal, the Court found that CPB was in fact required to demonstrate the requirement for Heyday (or any of the subcontractors) to have the visual contact by a spotter. The Court found that CPB had ample opportunity to do so.

Key Takeaway

Contractors need to be extremely cautious when issuing any form of correspondence to any subcontractors regarding compliance with their existing obligations (including those obligations that may be statutory or already a requirement under their specific contract) to avoid a subcontractor claiming a variation under a contract for construction. The decision also highlighted, once again, the importance of covering any possible issue that may arise within an adjudication application or response.

If you have any questions about any of the above, please do not hesitate to contact a lawyer in Coleman Greig’s Building & Construction team, who would be more than happy to assist you.

Disclaimer: This article is for general information purposes only and is not a substitute for legal advice. For more details, please read our full disclaimer.

Share:

Send an enquiry

Any personal information you provide is collected pursuant to our Privacy Policy.

Categories
Archives
Author

More posts

Year-end land tax and foreign surcharge – What you need to know

With 31 December 2025 fast approaching, if you have not done so already, we encourage you to review/double check your property arrangements and documentation. Assessments for land tax and foreign surcharge are issued around this time, and understanding your obligations now can help you avoid unexpected liabilities.

Key changes to Paid Parental Leave under Baby Priya’s Law

Last month, the Australian Government passed landmark legislation called the Fair Work Amendment (Baby Priya’s) Act 2025, providing additional protections for employees who receive employer-funded paid parental leave.

A father and daughter look at a tablet together
Changing a child’s name after separation

Separation can bring with it a range of emotions and the dispute between separating parents can be far and wide, including whether the surname of a child should be retained or changed.

Photo of a woman handing a child a bag
When child support doesn’t cover the costs – What you can do

In Australia, child support is governed by the Child Support (Assessment) Act 1989 (Cth). It is processed through Services Australia (Child Support) where a formulaic approach is taken to determine the amount of child support payable by one parent to the other.

A close up of a gavel
With or without you – Undefended hearings in Family Law

If a party has commenced family law proceedings in the Federal Circuit and Family Court of Australia (whether in relation to parenting or property matters) and the Respondent does not participate, the matter can, and eventually will, proceed without them.

Two horses in a paddock
Land tax exemption – Not as simple as you would think!

Land tax is an area that Revenue NSW is regularly targeting in their audits and investigations. In our Tax & Super practice, we have advised and worked with a number of clients on two common land tax exemptions – the principal place of residence exemption and the primary production exemption.

© 2025 Coleman Greig Lawyers  |  Sitemap  |  Liability limited by a scheme approved under Professional Standards Legislation. ABN 73 125 176 230