Extension of time clauses in building contracts

Ben Johnson ||

If you’re building or renovating, or working in the building and construction industry, it’s important that you know about extension of time clauses. An extension of time clause allows a party to a building contract to extend the time for completion of the building works beyond the original date of completion.

Extension of time clauses allow parties to continue project execution without financial penalties. In general, an extension of time is granted when the cause of the delay is beyond the parties’ control and interferes with the path to practical completion.

The validity of a claim for an extension of time under a construction contract depends on whether or not the construction contract contemplates the reason given for the extension. It is equally important to know the circumstances in which you are not entitled to claim an extension of time.

What are circumstances in which an extension of time be granted?

Construction contracts typically incorporate provisions defining the circumstances under which an extension of time may be granted. These provisions are as follows:

  • adverse weather conditions
  • adverse site conditions
  • delayed delivery of essential materials
  • variations that increase the scope of the work
  • latent conditions
  • changes in legislative requirements

Requesting an extension of time doesn’t grant an unrestricted privilege to the contractor to postpone the project without facing consequences.

What happens when there are multiple delays?

Multiple delays occurring at the same time are generally referred to in the contract as a concurrent delay. If one of the delays is a consequence of substandard performance, that party will be unable to claim an extension of time – regardless of whether the concurrent delay is impacting the date for practical completion. In circumstances where the concurrent delay isn’t a consequence of substandard performance, the causes of delay may be apportioned between the parties. An extension of time equal to the apportionment will be granted.

Parties must adhere to the provisions of the contract when seeking an extension of time for that claim to be valid. This assists with the management of any disputes or legal complications towards the end of a project.

Accordingly, the parties should carefully examine the contractual terms to confirm that the delay qualifies for an extension, and follow the precise steps laid out in the contract. Most contracts specify a timeframe within which a request for an extension of time is to be made. Often, this also includes a required notice period. Whether or not a time constraint for the provision of notice operates as a complete time bar to a claim for an extension of time depends on the particular drafting of the clause.

Complying strictly with these provisions is vital to ensure the validity of the extension of time claim. Failure to follow the provisions may lead to a complete bar to an extension of time claim altogether.

Many standard-form contracts also impose an obligation on the parties to take all reasonable steps to prevent delays and minimise their consequences.

For advice on whether you are eligible to claim an extension of time, please contact Coleman Greig’s Building & Construction Law experts. Our team regularly assist builders, contractors, developers and homeowners in the resolution of construction disputes.

Share:

Send an enquiry

Any personal information you provide is collected pursuant to our Privacy Policy.

Categories
Archives
Author

More posts

Are you liable for labour hire workers if they are injured?

Many employers (host employers) engage employees of labour hire companies, particularly in the building and construction, hospitality and manufacturing industries. However, what happens when one of these employees gets injured at the host employer’s work site? Who is liable for the injuries?

Part 1- The risks with cyber attacks and data breaches

Part 1 of a four-part series on your business’ responsibilities related to cyber attacks and data breaches. Cyber attacks and data breaches are the top business risk in Australia according to Aon’s 2023 Global Risk Management Survey.

Help! My builder won’t finish the job – what do I do?

It’s normal for building projects to experience setbacks during construction.  However, in extreme cases your builder may suspend works and leave the site or disappear without explanation. This article will explain your available options if your builder won’t return to the site, and how to avoid the common pitfalls which may affect your rights against your builder.

Is your intellectual property secure?

Securing intellectual property (IP) is critical in today’s competitive and increasingly digital landscape. From innovative startups to established enterprises, big or small, safeguarding your business’ intellectual assets can help ensure sustained competitiveness, legal protection and set you up to capitalise on your unique creations.

Out with the old (section 260) and in with the new (Part IVA)

Part IVA overcomes deficiencies of section 260 of the Income Tax Assessment Act (ITAA), exposed by judicial decisions. Part IVA was introduced, albeit with limitations on scope, to provide an appropriate balance between combatting tax avoidance without discouraging commercial and familial transactions.

Big changes ahead for the regulation of building products in NSW

All participants in the construction industry need to be aware of imminent changes to the laws regulating building products. The changes have been inserted into the Building Products (Safety) Act 2017 (NSW) but extend far beyond product safety to the suitability of use and quality of installation of those products.

Extension of time clauses in building contracts

© 2024 Coleman Greig Lawyers  |  Sitemap  |  Liability limited by a scheme approved under Professional Standards Legislation. ABN 73 125 176 230