Business people negotiating a contract

Clauses seeking Draft Payment Claims – are they void by virtue of the SOPA?

Ben Johnson ||

A recent decision of the Supreme Court of New South Wales has examined the circumstances where a clause within a contract requiring a “draft payment claim” may be seen to operate outside the scope of the Building & Construction Industry Security of Payment Act 1999 (NSW) (the Act). Ordinarily, such a process could be void in circumstances where the right to submit a payment claim only arose where the draft payment claim was provided.

East End Projects Pty Ltd v GJ Building and Contracting Pty Ltd [2020] NSWSC 819

Background

East End Projects Pty Ltd (Developer) and GJ Building & Contracting Pty Ltd (Builder) entered into a contract dated 1 June 2018 for construction works to take place at a project located in Newcastle (Contract). The Developer commenced proceedings seeking a declaration that a claim for payment submitted by the Builder dated 28 May 2020 was void under Act and also sought to restrain the Builder from seeking a determination on that payment claim under the Act on the basis that “a reference date” had not arisen at the time that the claim was served, by virtue of the Contract. 

The contractual mechanism for making a payment claim was as follows: 

  • Clause 37.1 required the Builder to provide a draft progress claim by the 25th day of each month for WUC (work under contract) done to the last day of that month (the Draft Progress Claim);
  • Clause 37.1(e) required the Builder to comply with clause 37.1, otherwise the draft payment claim was not a Draft Progress Claim pursuant to the Contract. It would then follow that no Draft Progress Claim would be considered to have been served until such time as the Builder complied with clause 37.1;   
  • Clause 37.2 required the Developer to issue a preliminary assessment of the amount that it considered to be due within 5 days of receiving the Draft Progress Claim; and,
  • Clause 37.3 provided that no earlier than 7 business days after the Draft Progress Claim had been submitted, the Builder had to provide a progress claim in final form (Final Progress Claim), and that the date referred to by clause 37.3 (being no later than 7 business days after the Draft Progress Claim) was to be the reference date for the purposes of the Act. 

The Builder did not follow the regime set out in clause 37.1 of the Contract. Instead, the Builder served a purported payment claim pursuant to the Act on 28 May 2020. The claim referred to a reference date of 30 April 2020.

The Builder submitted that clause 37 was void as a result of section 34 of the Act, and submitted that the reference date was the final day of each month in accordance with s 8(2)(b) of the Act as it stood at the time the Contract was entered into. The Developer, on the other hand, submitted that in accordance with s 8(2)(a) of the Act at the time the Contract was entered into (i.e. the old regime of the Act) meant that the reference date occurred by the process set out in the Contract, and as the Builder had failed to follow that process, there was no Reference Date. 

Decision

The Court found in favour of the Builder. The Court held that the Contract, despite the procedure contained within clause 37, did not identify a date on which a claim for a progress payment could be made, and thus, as at the date that the Contract was formed, the reference date was the last day of the month that the work was carried out as set out in s 8(2)(b) of the Act.

The Developer tried to argue that clause 37 gave rise to a reference date and sought to expedite payment of progress claims by virtue of the timeframe to review the Draft Progress Claim. The flaw within the clause 37 procedure was that if the Builder failed to submit the Draft Progress Claim by the 25th day of each month, then no reference date would arise. That requirement alone restricted the operation of the Act, which would mean that any such clause would be void as a result of section 34 of the Act.

A key takeaway from this case is that clauses that set out a different regime for payment are not necessarily void. The Court held that “the purpose of the time limit is to ensure that once the processes of the Act commence with the service of a payment claim, they occur promptly.  It is not the purpose of the Act to prevent parties from introducing other mechanisms in their contract to ensure that they are not caught by surprise”. Clearly, parties may be in a position to set out a similar approach to preparing payment claims as long as the Contract does not seek to contract out of the Act.

However, issues of this kind are likely to occur as a result of the October 2019 amendments to the Act, which allows (subject to the terms of the contract) the payment claim to be made on and from the last day of any month where works are undertaken or goods supplied. 

If you have any questions regarding the Building & Construction Industry Security of Payment Act 1999 (NSW) or require assistance, please do not hesitate to reach out to Coleman Greig’s Building and Construction lawyers, who are highly experienced with matters relating to the Security of Payment Act NSW and are able to provide expert, tailored advice – no matter the complexity of the matter at hand.

Share:

Send an enquiry

Any personal information you provide is collected pursuant to our Privacy Policy.

Categories
Archives
Author

More posts

Employers should exercise caution when dismissing during probationary period

Can you dismiss an employee during the probationary period? Yes, but a recent case is a lesson in caution. The recent Federal Court decision of ‘Dabboussy v Australian Federation of Islamic Councils’ is a warning to employers to consider the importance of timing if dismissing an employee during probation.

The business impacts from the Government’s new cyber security laws

Cybercrime ‘is a multibillion-dollar industry that threatens the wellbeing and security of every Australian’. In an effort to combat the impact on businesses and individuals, the Australian Government has introduced cyber security legislative reforms into the Parliament.

A guide to intrafamily adoption

Adoption is the process where a parent’s legal rights for their child are transferred to another person. The formal adoption of a stepchild or close relative is known as intrafamily adoption.

Passenger movement and visa data-matching by the ATO

Heading overseas for work or a holiday? Taxation issues, including tax residency, should be on front of mind when departing from or arriving to Australia. Why? Because the Australian Taxation Office (ATO) can follow your footprints and, if you’re not careful, spring unexpected taxes on you.

Is it really necessary for my executor to have so many powers?

People often question why the executor of their estate needs to have so many powers. Simply put – if your executor isn’t given any additional powers by your Will, then they are limited to what is set out in the Trustee Act. One area that this can lead to issues in, is the family home – particularly if beneficiaries aren’t in agreement.

Essential terms of a commercial lease

A commercial lease is a contract that details the rights and obligations of a tenant and landlord. So, what are the necessary terms of a commercial lease?

Responding to data breaches

In the final part of our four-part series on your business’ responsibilities related to cyber attacks and data breaches, Special Counsel John Bennett how businesses should respond to data breaches, including application and requirements of the Notifiable Data Breaches Scheme.

Security of personal information

Part 3 of a four-part series on your business’ responsibilities related to cyber attacks and data breaches where Special Counsel, John Bennett provides an overview of some court decisions and proceedings where ‘security’ of personal information has come into issue.

Parental alienation in Family Law

The concept, Parental Alienation Syndrome, was initially brought about by American psychiatrist Richard Gardner in 1985. The term parental alienation is used to describe a situation where one parent is involved in psychologically manipulating their child to turn against the other parent.

Are you liable for labour hire workers if they are injured?

Many employers (host employers) engage employees of labour hire companies, particularly in the building and construction, hospitality and manufacturing industries. However, what happens when one of these employees gets injured at the host employer’s work site? Who is liable for the injuries?

© 2024 Coleman Greig Lawyers  |  Sitemap  |  Liability limited by a scheme approved under Professional Standards Legislation. ABN 73 125 176 230