Male Judge Writing On Paper

Courts Cannot Overturn Building & Construction Decisions Based on Non-Jurisdictional Errors

On Valentine’s Day 2018 the High Court handed down a significant decision affecting the building and construction industry.  This particular decision has defined the parameters of the court’s powers with regard to overturning an adjudicator’s determination made pursuant to the Building and Construction Industry Security of Payment Act 1999 (NSW) (SOPA).

In short, the High Court has determined that the courts do not have the power to overturn an adjudicator’s determination based on a non-jurisdictional error of law on the face of the record.  What this effectively means, is that unless an adjudicator has made an error of jurisdiction in his/her determination, a court has no power to overturn that ruling.

In turn, adjudicators are now able to make determinations knowing that any incorrect interpretation of a building contract will not be subject to judicial review.

Taking this into consideration, Coleman Greig Lawyers advises that it is of paramount importance that all parties applying for adjudication ensure that their T’s are crossed and I’s are dotted, as they will have no recourse to the courts in the event of receiving an unfavorable decision based on a non-jurisdictional error of law.

Facts of the case:

The decision was handed down in the matter of Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4.

The relevant facts of the case were as follows:

  • Probuild Constructions (Aust) Pty Ltd (Probuild) and Shade Systems Pty Ltd (Shade Systems) were parties to a building sub-contract.
  • In December 2015, Shade Systems served on Probuild a claim for a progress payment under SOPA in the sum of $294,849.33 (excluding GST).
  • Probuild served a payment schedule disputing Shade Systems’ claim and contended that it was entitled to a set off in the sum of $1,089,900 for liquidated damages.
  • Shade Systems applied for adjudication, and the adjudicator in turn determined Probuild to pay $277,755.03 for the progress payment.
  • Probuild applied to the Supreme Court of NSW seeking an order quashing the determination of the adjudicator.  At first instance, the primary judge granted the order, finding that there was an error of law and ruled that the adjudicator incorrectly considered that no entitlement to liquidated damages arose until practical completion or termination of the subcontract.
    Further, the court determined that it was an incorrect consideration on the part of the adjudicator that Probuild needed to demonstrate that Shade Systems was at fault for the delay for which the liquidated damages were claimed.
  • Shade Systems appealed against the decision to the Court of Appeal.  The only question considered on appeal was – “whether the Court’s power under section 69(3) of the Supreme Court Act 1970 (NSW) to quash a determination for a non-jurisdictional error of law on the face of the record was available in the case of SOPA adjudications determinations or whether Parliament had intended that it be excluded”.
  • The Court of Appeal overturned the primary judge’s decision and found that the jurisdiction of the courts was ousted.  Probuild subsequently appealed to the High Court.

Decision of the High Court:

The High Court ultimately agreed with the Court of Appeal.  The majority of the court ruled that SOPA demonstrates a clear parliamentary intention to exclude the Supreme Court’s ability to make a judgment overturning any adjudicator’s determination based on a non-jurisdictional error of law on the face of the record.

The High Court held that “A non-jurisdictional error of law may have serious consequences.  But those consequences are dealt with by s 32 of the Security of Payment Act” (paragraph 51).  The court clarified that the erroneous decision of an adjudicator could be resolved through civil proceedings under the building contract and if necessary, a restitutionary order can be sought.

If you have any queries regarding the above case, or would like to speak with someone in Coleman Greig’s Litigation & Dispute Resolution team regarding your own matter – please don’t hesitate to reach out to:

Share:

Send an enquiry

Any personal information you provide is collected pursuant to our Privacy Policy.

Categories
Archives
Author

More posts

roles in the strata scheme
Understanding roles in the strata scheme

A strata scheme is a building or group of buildings that have been divided into lots which can be apartments, villas, offices, units or townhouses. This will be articulated in the strata plan.

Airbnb home
Can I put my home on Airbnb?

Airbnb is a form of short-term rental accommodation. To add your property to Airbnb in NSW, you are required to meet several laws and regulations governing short-term rentals.

liquidators required to seek approval
When are liquidators required to seek approval to retain legal counsel?

When does a liquidator (or the company he or she is appointed to) need court, creditor, or committee approval to validly retain a solicitor to act in a liquidation matter which is likely to extend for longer than three months?  The answer to this question has only recently been settled.

Proposed changes to building
Proposed changes to building and construction law in NSW

The Building Bill 2022 (the Bill) is the key avenue through which the NSW Government has proposed to reshape the culture of the building and construction industry by eliminating poor performance and improving the quality of building statewide.

Dismiss an employee
Can you dismiss an employee who fails to return to the office?

Slowly but surely, most employers are requiring employees to return to the office for at least a portion of their working week. Some employers continue to struggle with employees resistant to returning to the office or those who have an expectation that they can continue to work from home whenever it suits them.

Phoenixing in Construction
New powers to combat phoenixing in construction

The rise of phoenixing in the building and construction industry in Australia in recent years has proved a significant challenge to regulators. Mismanagement of time or cashflow can quickly propel businesses into insolvency.

© 2024 Coleman Greig Lawyers  |  Sitemap  |  Liability limited by a scheme approved under Professional Standards Legislation. ABN 73 125 176 230